Lilama 69 - 1: Finishing 95% of the maintenance work for Dung Quat Oil Refinery plant

01/07/2014 08:36

Since early May 2014 up to now, Lilama 69-1 JSC (member of LILAMA Corporation) has been participating in the work of maintenance and overhaul for Dung Quat Oil Refinery the second time.

Dung Quat Oil Refinery Plant (Quang Ngai)

     After a month carrying on the work, with the effort of engineers, workers at site, up to now, the company has finished more than 95% of the work volume in the contract, particularly: finished the elastic equipment and spool pipelines of the plant; finished the contract of heat gain for pipeline treatment, the contract of reinforcement for steel structure beam and operation floor of the plant, the contract of manpower supply for maintaining turbine of the plant power generator and manpower supply for the entire maintenance; the contract of repairing 4 cyclones has been nearly finished.

     Mr Doan Huy Hoang, Lilama 69-1's manager of maintenance work said that was an important national project so the requirements of technique and safety are very severe. All procedures, material, equipment and manpower had been checked strictly by Contractor O&M. With the best determination and effort of the workers, they have finished the contract packages well in accordance with the undertaken schedules and highly appreciated by the Owner.

    For the time being, the plant overall maintenance has basically met the defined requirements. The oil refinery plant has also conducted to restart its power factory so that their workshops can operate again sooner.

Duy Tinh, Ba Luc