Nghi Son oil refinery project: has successfully installed super-weight equipment

02/03/2015 09:07

Recently, in Nghi Son oil refinery project (Tinh Gia, Thanh Hoa), LILAMA Corporation in coordination with NIPPONG EXPRESS (NEX) has conducted to install the Reactor weighed 655 tons successfully. This is one of the important equipment of the plant.

     To install the above equipment, the performer had to use a crane with capacity of 1350 tons, an other crane of 800 tons and installed totally 12 equipment of this kind. LILAMA 69-1 was responsible for calibrating the equip. and supporting the installation for the highest result. Right after finishing the erection work, LILAMA 69-1 will perform a series of other work such as installing steel structures and piping around the above equipment.

Mr Tran Dinh Dai (the 5th from the right) - Lilama Project Director in Nghi Son guides workers at site

     In Nghi Son oil refinery project, LILAMA has been responsible for manufacturing and installing steel structures, installing equipment, pipelines, tanks and vessels … with the moment manpower of 2,500 people from 11 member companies participating in the performance.

Duy Tinh - Viet Cuong