Successfully Installing main beam for boiler of Expansion Duyen Hai 3 thermal power plant

13/09/2016 15:05

Recently (27/8/2016), in Expansion Duyen Hai 3 thermal power plant, Dan Thanh commune, Duyen Hai district, Tra Vinh province, Lilama 18 JSC has conducted to install main beam for boiler item of the plant.

Main beam was installed accurately at the height of 74m

   5 combinations of main beams in total which weighed 32 to 94 tons has been installed successfully, safely and accurately at the height of 74m.

     Lilama 18 JSC is responsible for installing Boiler 1 with capacity of 660 MW. Since March 2016 upto now, Lilama 18 has accomplished nearly 7,000 tons of equipment in the total of 26,000 tons of boiler. As planned, Boiler 1 of the project will be finishe by Lilama 18 in January 2017. This will be an important time to switch to the stage of installing pressured equipment for boiler. In addition to boiler item, Lilama 18 also undertakes to install electrical system and controlling system for the whole project.

     Expansion Duyen Hai 3 thermal powe plant has 01 machine unit of 660 MW with annual power yield of 3.9 billion kWh. Its owner is Power Generating Corporation (Genco1) from Electricity of Vietnam (EVN).

Mai Phuong