Lilama has successfully installed rotor of machine unit 1, Lai Chau hydro power plant

14/10/2015 08:30

This morning (14/10) at Nam Hang commune, Nam Nhun district, Lai Chau province, Lilama 10 JSC has successfully installed the rotor of machine unit 1 in Lai Chau hydro power plant. The rotor which weighs 1000 tons with diameter of 15.587m and height of 2.816m was installed by 2 cranes with lifting capacity of 1,200 tons.

    

     Previously, the work of checking & preparation for taking down rotor such as: assembling work, calibrating work, high-voltage testing work, checking the lifting equipment, Stator - generator, Turbine ... had been finished accurately by Lilama 10 managing board, satisfying the defined technical specifications. 

     At 5:10 a.m, the Rotor which weighs 1000 tons with diameter of 15.587m and height of 2.816m began to be taken to the installation position (tubine well); and after nearly 5 hours, it was put into the position safely and accurately in witness of Owner and Supervision Consultant. The successful taking down of rotor of machine unit 1 in Lai Chau hydro power plant marks an important schedule milestone, assuring to put machine unit 1 into operation in the end of this year.

     After taking rotor to its installation position, Lilama 10 concentrated to connect the high-voltage compressed air system, electrical system, activate brakes … so as to fulfil the installation work. At the moment, preparation work for installing machine unit 2 is being deployed actively by Lilama 10. Facing many hardships such as bad weather, late arrival of equipment, narrow execution area … but the installation workers believe the Lai Chau hydro power plant project will be accomplished soon, ahead of schedule, in the end of next year.

Some photos of installing rotor of machine unit 1 in Lai Chau hydro power plant:

Stator had been finished in preparation for rotor installation

Rotor had been assembled, 30m far from its installation position

Lilama workers began to install rotor

Previously, rotor had been cleaned

Rotor was moved by 02 cranes with lifting capacity of 1,200 tons

After nearly 1 hour, rotor was taken to the position

With the weight of 1000 tons, diameter of 15m, the distance between rotor & Stator was just 31.5mm, so the installation work was conducted very carefully and accurately to each smallest act

After 5 hours, rotor has been installed successfully into its position

Viet Cuong - Duy Tinh