Recently, LILAMA10 JSC has officially signed contract of construction for Sendje hydro power plant (Ghi Nê Xích Đạo) with Duglas ALLIANCE Co. of the United Kingdom.

     After a time of study, survey and negotiation, LILAMA10 JSC has officially signed contract of construction & installation of equipment for Sendje hydro power plant belonging to Ghi Nê Xích Đạo with Duglas ALLIANCE Co. of the United Kingdom, the value of contract phase 1 is approximately USD4.6 million.

    According to the contract, LILAMA10 is now conducting the preparation work and they will send about 150 labourers consisting of engineers, foremen, operators and technicians to the project site. The project will be commenced from 10/2015 and all work volume under the contract will be finished within 21 months.

    This is a contract of construction & installation which is the same as some others being performed by LILAMA10 inside and outside the country. Through direct survey, the social conditions, weather and infrastructures are quite convenient for labourers. For the time being, LILAMA10 is negotiating to undertake some other items of the project.

Some features of Sendje hydro power project:
- Location: on Wele river of Sendje town, 40km from Bata city.
- Owner: the Government of Ghi Nê Xích Đạo.
- EPC Main Contractor: Duglas ALLIANCE Co.,Ltd - England
Main specifications:
- Capacity: 200 MW
- Number of machine units: 04.